The project titled ROAD CONSTRUCTION USING HIGHWAY PLANNING AND OBSTRUCTION PREVENTION aims to address one of the major issues that the Indian road construction department is facing.

Road Construction Using Highway Planning and Obstruction Prevention

Table Of Contents

  • Abstract
  • Introduction
  • Project Requirements
  • Literature Survey
  • Block Diagram
  • Pseudo Code
  • Output Screentshot
  • Conclusion
  • References
  • Our Team

1. Abstract

The project titled ROAD CONSTRUCTION USING HIGHWAY PLANNING AND
OBSTRUCTION PREVENTION aims to address one of the major issues that the Indian
road construction department is facing. These days we notice that a large number of roads
are not in proper condition and many of them require restoration. Many of which are in
high usage and require immidiate repair. Our project aims to help athorities with
providing them the most profitable path for road contruction for a given map and the
sequence in which these roads can be addressed so that it would be convenient for both
the authorities as well as the general public.Our project collects various forms regarding
the map for the road that needs to be constructed, with this data we find the most shortest
and profitable path possible . Then we collect data for utility and traffic for all the roads
,then we normalize the data collected and generate a appropriate sequence in which the
road construction should be addressed. We have also included a deadline section so that
the roads that take more then the allocated time are highlighted and if necessary removed.
Also, a check for hindrance detection is added which can be used when we have limited
number of resources and a proper allocation of these resources is required. For this we
take inputs for resources which can refer to asphalt, machinery, mortar etc. Then we
require maximum resources needed for each road, amount of resources allotted for each
road, and available resources, based on which a safe sequence is generated that prevents
any unwanted stoppage of work.

2. Introduction

In countries like India where we are seeing a steep rise in the overall population there arise a
necessity of new habitat and scouring of vacant land to make new buildings, accommodations
and environments which are connected by roads. As per the statistics we get to know that a
total of 2098624 km of road was laid in India alone during the period 2001 to 2005 and these
numbers are continuously rising with each passing year. So the maintenance and construction
of new roads require a tremendous work force and attention from the government. So it
becomes necessary to design a proper algorithm that can manage the overall process of road
construction.

So the first part of the project deals with the task of getting the parameters through which a
road can be assigned a particular priority and accordingly can be used for further estimations
and calculations. So for this purpose we consider 3 parameters associated with a particular
road namely the size,utility and the traffic associated with each road . For the purpose of
getting the road size we employ yet another renowned and precise algorithm known as
djikstra algorithm to get the shortest road length

Scheduling is one of the most widely used techniques to using which any operation involving
several tasks can be ordered in such a way so that easy execution of the entire operation
becomes possible in the most efficient way possible avoiding any sort of errors and
confusions. The programme that does the task of scheduling is termed as a scheduler. Now
the scheduling used in the project involves priority scheduling without the use of pre-
emption(the reason for the same is explained in the later part of the project) ,So here the
algorithm decides how to schedule the various construction processes in the given region
based on their priorities , which in-turn is decided on the basis of various factors which are
mentioned in the above paragraph of the project. So all the constructions will be handled
accordingly.

In the second part of the proposed work, We tried to focus on the very common issue of delay
and stopping of the entire construction process due unavailability of various resources
involved in the construction process so we compared this scenario with the dead-lock
condition that arises in the operating systems while assigning resources to various running
processes and this lead us to use the same algorithm that we use in operating systems that is
the bankers algorithm for our project as well using various resources involved in the road
construction process so as to avoid any condition of an absolute deadlock state in our
construction process. The resources we use are discussed in later part of the project .So using
this bankers algorithm we make sure that at no situation should occur where for the lack of
required resources, all work gets stopped or hindered. So, the implementation of this
algorithm becomes necessary. The safe sequence advices in what order to proceed so that by
the available resources, all tasks can be completed.

3. Project Resource Requirement

  • Software Requirements

    This project has been created using CODE BLOCKS
    C Programming language has been used for the code

  • Hardware Requirements

    Intel i3/i5/i7/i9

    Windows 7/8/8.1/10

    4 GB RAM

    4.0 GHz processor

4. Literature Survey

  • 1.Title : A Comparative Review of CPU Scheduling Algorithms
    AUTHORS- Mohd Shoaib and Mohd Zeeshan Farooqui

    • CONFERENCE PAPER Conference: Proceedings of National Conference on Recent
      Trends in Parallel Computing (RTPC - 2014)
    • At: Aligarh, India

    Published in November 2014

ADVANTAGES: CPU Scheduling decides which tasks are to be ordered in what way so
that a particular algorithm is followed to queue the processes.
DISADVANTAGES:There is no involvement of premptive SRTF in the paper , the
comparision is done only considering the non preemptive SRTF

  • 2.Title : A Comparative Study of CPU Scheduling Algorithms
    AUTHORS: Neetu Goel ,Dr. R.B. Garg

    • Journal: International Journal of Graphics & Image Processing IJGIP [ VOL-2 , Issue-
      4],

    Published in November 2012

ADVANTAGES: This research paper shows that First Come First Serve (FCFS) &
Shortest Job First (SJF) is generally suitable for batch operating systems and Round
Robin (RR) & Priority Scheduling (PS) is suitable for time shaing systems.

DISADVANTAGES: No new algorithm was proposed in this paper

  • 3.Title: Design and Implementation of Multi parameter Dijkstra’s Algorithm: A Shortest
    path algorithm for real road networks.
    AUTHORS: Nishtha Kesswani, Dinesh Gopalani

    • Journal: International Journal of Advances in Engineering and Research [Volume 2,
      Issue 3],

    Published in september 2011

ADVANTAGES: Taking the real road networks into consideration, this paper suggests a
modification of Dijkstra's algorithm, the multi-parameter Dijkstra’s algorithm (MPD) that
considers multiple parameters into consideration. Apart from the distance between any
two nodes, it considers factors such as time taken to travel from the source to the destination,
congestion of the route etc. so that the user can select the desired route based
on his/her preferences.

DISADVANTAGES: Cosiderable importance was not given to traffic and utility of roads

  • 4.Title: Performance of deadlock avoidance algorithms in flexible manufacturing systems.
    AUTHORS: Maria P. Fanti,Bruno Maione,Saverio Mascolo,Biago Turchiano

    • Journal: Journal of Manufacturing Systems(Elsevier) [Volume 15, Issue 3]

    Published in 1996

ABOUT: This paper compares performances of some deadlock avoidance policies. First,
theoretical analysis is carried out by introducing a criterion for ordering different policies by
flexibility in resource allocation. Second, avoidance policies are applied to some case
studies, which are simulated in detail. The simulation analysis confirms the theoretical
results showing that the algorithms allowing larger flexibility in resource allocation lead to
better performance indices.

  • 5.Title: Approaches for Deadlock Detection and Deadlock Prevention for Distributed
    Systems.
    AUTHORS: Dhiraj Gupta, V.K Gupta (Department of Computer Science,NIMS
    University,Jaipur,Rajasthan, India

    • Journal: Res. J. Recent Sci., Volume 1, Issue (ISC-2011)

    Published in 2011

ABOUT: This paper, discusses about deadlock detection techniques and present
approaches for detecting deadlocks in Distributed Systems. In many other aspects of
distributed systems, they are harder to detect, avoid, and prevent. Deadlocks are a
fundamental problem in distributed systems. Deadlock detection is more difficult in systems
where there is no such central agent and processes may communicate directly with one
another.

  • 6.Title: A Review Study on the CPU Scheduling Algorithms.
    AUTHORS: Shweta Jain(Department of Computer Science, Shri R.G.P. Gujarati
    Professional Institute) , Dr. Saurabh Jain(Institute of Computer Applications, Shri Vaishnav
    Vidyapeeth Vishwavidyalaya)

    • Journal: International Journal of Advanced Research in Computer and
      Communication Engineering IJARCCE [Vol. 5, Issue 8]

    Published in August 2016

ABOUT: In this paper, a review of techniques proposed by different authors are discussed
which is helpful to design Operating Systems and new researches in Scheduling. System
designers have many complex decisions that they are required to make before finalizing
their designs. The selections of the appropriate processor scheduling algorithms allow them
to tailor the design to perform at the highest level of performance, reducing overall idle
time. Design specifications will drive decisions such as responsiveness, preemption, and
reliability. These combinations can benefit both single processor and multiprocessor
systems if selected in the proper combination.

  • 7.Title: Research on the optimization of Dijkstra’s Algorithm and its application.
    AUTHORS: Arjun RK, Pooja Reddy, Shama, M.Yamuna

    • Journal: International Journal of Science, Technology & Management IJSTM [Vol. 4,
      Issue 1]

    PUBLISHED IN APRIL 2015

ABOUT: This paper mainly studied the application of the shortest path algorithm based on
the data structure, and proposed the improved Dijkstra’s algorithm, which optimized
selection of the shortest path node and data storage structure and organization. Studies
showed that, compared with the traditional Dijkstra’s algorithm, the optimized Dijkstra’s
algorithm which has optimized the space complexity, time complexity and storage
combination reduced the storage space, reduced data redundancy and greatly improved the
running rate. It was clearly shown that the optimized algorithm is more applicable to
calculate the shortest path.

5. Block Diagram

Explanation:

  1. First we take inputs for the number of roads
  2. Then we will take inputs for the formation of map in form of graph for all the different
    roads
  3. Then based on the graph we will apply dijakstra algorithm and find the shortest distance
    possible between the desired cities
  4. This distance is saved as a parameter of size for the roads
  5. Also the route of the shortest path will be displayed
  6. Then we read the utility, traffic and deadline for all the roads
  7. Based on these inputs we check for clashing between the priorities
  8. If present the clashing is handled
  9. Then the required sequence is generated
  10. Based on the sequence we find the waiting and completion times for the roads
  11. Now we check if the roads can be completed within their allocated time
  12. If deadline is crossed then an error message “DEADLINE NEEDS TO BE
    COMPROMISED IS DISPLAYED”
  13. If dead line is not passed the generated sequence is displayed and we move to the second
    part of project
  14. Here we read the number of resources needed for each road,maximum resources needed
    for each road, amount of resources allotted for each road, and available resources
  15. Based on which a safe sequence is generated
  16. If sequence is not generated then an error message is displayed

6. Pseudo Code

PSEUDO CODE FOR DIJAKSTRA FOR FINDING SHORTEST PATH FOR ROADS ->
INPUTS AND ALGORITHM ->

1- FIRSTLY, WE WILL TAKE THE INPUT FOR THE FORMATION OF MAP FOR
DIJAKSTRA

2- THIS INVOLVES TAKING THE INPUT FOR NUMBER OF CITIES(NODES);
NUMBER OF ROUTES CONNECTING THEM(EDGES); AND THE DISTANCE
OF THE ROUTES(WEIGHT OF EDGES)

3- THEN WE APPLY THE DIJAKSTRA ALGORITHM FOR THE MAP(GRAPH)
AS FOLLOWS

function Dijkstra(Graph, source)

       dist[source] := 0                              // Distance from source to source is set to 0
       
       for each vertex v in Graph:                    // Initializations
       
       if v ≠ source
             dist[v] := infinity                          // Unknown distance function from source to each node                                                                 set to infinity
        add v to Q                                     // All nodes initially in Q
        
        while Q is not empty:                          // The main loop
              v := vertex in Q with min dist[v]              // In the first run-through,this vertex is the source                                                                 node
              remove v from Q
        
        for each neighbor u of v:                      // where neighbor u has not yet been removed
                                                          from Q.
              alt := dist[v] + length(v, u)
              if alt < dist[u]:                              // A shorter path to u has been found
                    dist[u] := alt                                 // Update distance of u

return dist[]

4- THEN FROM THE OBTAINED DISTANCE ARRAY WE FIND THE
DESTIANTION VERTEX

5- THE DISTANCE IS THEN SAVED AS SIZE FOR THE ROAD

PSEUDO CODE FOR PRIORITY SCHEDULING FOR SCHEDULING THE ROADS
INPUTS AND ALGORITHM ->

1- FIRSTLY, WE TAKE THE INPUT FOR THE NO OF ROADS.

2- NOW HERE WE ASSIGN THE PRIORITIES FOR EACH ROAD BASED ON A
NO OF PARAMETERS NAMELY SIZE, UTILITY, TRAFFIC.

3- NOW FOR SIZE WE EMPLOY DIJKSTRA’S ALGORITHM FOR GETTING THE
LEAST POSSIBLE PATH FOR THE CONSTRUCTION OF OUR ROAD.

4- FIRST, WE GENERATE A SEQUENCE IN WHICH THE CONSTRUCTION
WORK SHOULD PROCEED. THIS SEQUENCE IS GENERATED ON THE
BASIS OF PRIORITY SCHEDULING ALGORITHM. SO, IN THIS ALGORITHM
WE USE THE ABOVE PARAMETERS AND SUM THEM UP AND NORMALISE
THEM DOWN TO 1-100 TO GET THE PRIORITY FOR ANY CONSTRUCTION
PROJRCT.

5- Which is done by using:

Priority Pi of road i = (Si / Sigma(Si)) *100

Where Si for any given road i is submission of size, utility and traffic

6- PRIORITY SCHEDULING WITHOUT PREEMPTION IS APPLIED AS
FOLLOWS

function Priority Scheduling(Processes,Priority,Arrival_Time,Burst_Time)
        
        Current_Time := 0                                //Current Time of the CPU
        
        while (All Processes are not executed):
               
               P:=All the processes whose Arrival_Time=<Current_Time
               
               i := index of the process with highest Priority in P
               
               If(No index is found)                            //CPU in ideal state , no process arrived yet
               
               Current_Time++
        
        Else
               
               Execute the process P[i]
               
               Current_Time=Current_Time+Burst_Time[i]
               
               Completion_Time[i] = Current_Time
               
               Turnaround_Time[i] =Completion_Time[i] - Arrival_Time[i]
               
               waiting_time[i] = turnaround_time[i]- burst_time[i]
               
               response_time[i] = start_time[i] - arrival_time[i]

7- ALSO FOR THE ABOVE CASE IF A SCENARIO OCCURS WHERE THE
PRIORITIES OF TWO ROAD CLASHES THEN FIRST WE GO FOR THE
UTILITY OF THE ROADS TO DECIDE THE PRIORITY THEN TRAFFIC AND
THEN SIZE.

8- SO ONCE WE HAVE GIVEN ALL THE REQUIRED INPUTS FOR
PARAMETERS , WE WILL ALSO BE ASKING THE USER TO ENTER THE
DEADLINE AS WELL AS THE EXPECTED COMPLETION TIME.
OUTPUTS OBTAINED ->

9- SO, AFTER SUCCESSFUL EXECUTION WE WILL BE GETTING THE
WAITING TIME AS WELL AS THE TOTAL TIME CORRESPONDING TO
EACH OF THE CONSTRUCTION PROCESSES.

10- IN ADDITION TO THAT WE WILL BE GETTING THE TURNAROUND TIMES
FOR EACH CONSTRUCTION AS WELL.

PSEUDO CODE FOR BANKERS ALGORITHM ->

1- SO, THIS ALGORITHM IS USED TO GIVE A SAFE SEQUENCE FOR THE
CONTINUATION OF CONSTRUCTION PROCESSES AT ALL TIMES.

2- WE TAKE THE INPUT OF

  • NO OF RESOURCES THAT ARE REQUIRED FOR THE CONSTRUCTION
    OF THE ROAD
  • THE ALLOCATION OF THESE RESOURCES THAT THE CONSTRUCTION
    AUTHORITY HAS DONE.
  • THE MAXIMUM RESOURCES THAT A PARTICULAR ROAD WILL
    REQUIRE AT ANY STAGE IN THE CONSTRUCTION PROCESS.
  • AND LASTLY THE AVAILABILITY OF THESE RESOURCES WITH THE
    CONSTRUCTION RESOURCES CURRENTLY.

3- AFTER ALL THESE INPUTS THE STANDARD NEED MATRIX OF THE
BANKERS ALGORITHM IS CALCULATED.

4- NOW FOR EACH PROJECT WE COMPARE WHETHER THE ALLOCATION IS
GREATER OR EQUAL TO THE NEED ARRAY FIGURES FOR THE
FOLLOWING PROJECT IN CASE SUCH A PROJECT IS FOUND WE PROCESS
IT AND THEN TAKES BACK THE ALLOCATED RESOURCES FROM THAT
PARTICULAR PROJECT AND GIVES IT TO THE AVAILABLE ARRAY .

5- THE SAME PROCESS IS REPEATED UNTILL WE DON’T SATISFY THE NEED
OF EACH PROJECT.

6- IN CASE WE FAIL TO FIND A PROCESS AT ANY PARTICULAR STAGE
SUCH THAT THE NEED OF NO PROCESS IS SATISFIED BY THE
AVAILABLE MATRIX WE PRINT “ NO SAFE SEQUENCE FOR
CONSTRUCTION WITH THE AVAILABLE NO OF RESOURCES”.

7- OTHER WISE WE PRINT THE SEQUENCE WHICH NEEDS TO BE FOLLOWED
FOR SAFE COMPLETION OF ALL PROJECTS.

7. Output Screenshots

OUTPUT-1 (Deadline compromised,Clash of priority,Safe sequence exists)

OUTPUT-2 (No Deadline issue, No Clash of priority,Safe sequence does not exist)

8. Conclusion

The proposed model is highly recommended as it successfully implements all the ideas that
were initially put forth. The main purpose was to find out order in which a group of roads are
mended or constructed so that within short time and correct resources, the roads are dealt
with, without any ambiguity, prioritizing the important ones over the others. So in this way
we get an ideal sequence for a large set of construction processes ongoing in the entire
country which would not have been possible to deal with manually .The designed model is
also able to find the most profitable route for the road construction whose map was given to
us. By applying dijkstra algorithm to this map we were able to find the profitable route for
construction .The model is also able to checks the safe sequence based on the data available
to the authorities, whereby it says if the certain available resources is enough for the safe
mending of all the given roads.

Now we discuss that The reason to implement Priority Scheduling over the other methods is
to ensure that the correct purpose is met and solved. In the given scenario, using other
efficient algorithms like Shortest Job First is not feasible because the prior knowledge of
every parameter is not sometimes possible because continuous damage of various other roads
is possible in real life, and hence they will keep adding to the list making it impossible for
roads of higher priorities to get completed. Also, the interruption of a going on task and
resuming of others, while resuming the first one later is not possible in this scenario because
an important road cannot wait forever once mending it has been started. The traffic and utility
of that particular road does not allow it to wait for others. Hence, the best possible algorithm
for the implementation was Priority Scheduling.

9. References

1- Mohd Shoaib and Mohd Zeeshan Farooqui, A Comparative Review of CPU
Scheduling Algorithms, Proceedings of National Conference on Recent Trends in
Parallel Computing (RTPC - 2014), NOVEMBER 2014

2- Neetu Goel ,Dr. R.B. Garg,A Comparative Study of CPU Scheduling Algorithms,
International Journal of Graphics & Image Processing IJGIP [ VOL-2 , Issue-4],
November 2012

3- Nishtha Kesswani, Dinesh Gopalani, Design and Implementation of Multi
parameter Dijkstra’s Algorithm: A Shortest path algorithm for real road networks.
International Journal of Advances in Engineering and Research [Volume 2, Issue
3], September 2011

4- Maria P. Fanti,Bruno Maione,Saverio Mascolo,Biago Turchiano, Performance of
deadlock avoidance algorithms in flexible manufacturing systems. Journal of
Manufacturing Systems(Elsevier) [Volume 15, Issue 3], 1996

5- Dhiraj Gupta, V.K Gupta ,Approaches for Deadlock Detection and Deadlock
Prevention for Distributed Systems, Res. J. Recent Sci., Volume 1, Issue (ISC-
2011),2011

6- Shweta Jain , Dr. Saurabh Jain, A Review Study on the CPU Scheduling
Algorithms, International Journal of Advanced Research in Computer and
Communication Engineering IJARCCE [Vol. 5, Issue 8], AUGUST 2016

7- Research on the optimization of Dijkstra’s Algorithm and its application,
International Journal of Science, Arjun RK,Pooja Reddy,Shama,M.Yamuna,Technology
& Management IJSTM [Vol. 4, Issue 1], APRIL 2015

Our Team

Pilla Vaishno Mohan, Mateen Jamal, Anant Tiwari and Ayush Sharma